Texas cement plants in 2026: planned projects, map, and TCEQ permit requirements.

Texas is the largest cement-producing state in the country — and it still can't make enough. Every expansion, kiln modification, and greenfield proposal runs through TCEQ first, and cement plants carry some of the heaviest air permitting requirements of any facility type in Texas.

Updated July 13, 2026 · PermitPulse
The state of play

Population growth, highway programs, and the data center construction boom keep the state structurally short on cement, so producers are expanding: Amrize is putting a $900 million North American investment program to work at Midlothian, and CRH's acquisition of the 2.1 million tpy Hunter plant near New Braunfels made it the state's largest producer at roughly 3.2 million tons per year.

Market context

The Texas cement market, by the numbers.

Cement demand tracks construction, and no state builds like Texas. TxDOT's highway program, DFW and Austin–San Antonio growth, and concrete-hungry data center and industrial construction keep the state structurally short.

#1
Cement-producing state
~10 integrated plants, plus terminals importing to cover the shortfall
$900M
Amrize Midlothian program
New silos, 11 truck lanes, +100,000 tpa by 2027
3.2M tpy
CRH — now the largest producer
After acquiring the 2.1M tpy Hunter plant near New Braunfels
100 tpy
PSD major source threshold
Cement plants are federally listed — every integrated plant is PSD-major

Because cement plants are major sources, every expansion shows up in TCEQ's permit docket long before any announcement — permit amendments are the earliest signal of who's adding capacity.

The pipeline

Permitted & planned cement plants in Texas.

The most recent TCEQ air permit filings matching cement plant projects — a sample from the live feed, updated as new applications and amendments hit the docket.

Live from the TCEQ docket — 2,387 matching filings
Track Texas cement plant permits as they're filed.

PermitPulse watches the TCEQ docket daily and emails you when a new cement application or amendment hits the docket.

Start free →
No credit card · 1 watch free forever
Geography

Texas cement plant map.

Integrated cement plants (kilns), grinding facilities, and major terminals cluster where limestone geology meets big-metro demand — most visibly Ellis County south of Dallas and the IH-35 corridor between San Antonio and Austin.

See new cement filings on the map, in your inbox.

Set a watch on the counties you care about and get an alert the day a matching TCEQ application appears.

Start free →
No credit card · 1 watch free forever

Where Texas cement is made

Ellis County / Midlothian

The "Cement Capital of Texas": multiple integrated plants (Amrize, Ash Grove, Martin Marietta) feeding Dallas–Fort Worth. Also home to the state's strictest kiln NOx rules (see below).

New Braunfels–San Antonio corridor

The Hunter plant (CRH), Capitol Aggregates, and Alamo Cement sit on the Edwards limestone belt along IH-35, serving the fastest-growing corridor in the state.

West Texas & Panhandle

Plants at Odessa and Amarillo serve the Permian and plains markets.

Gulf Coast terminals

Houston-area and coastal terminals import cement and clinker to cover the structural supply gap.

The regulatory gauntlet

What TCEQ permits are required for cement plants in Texas?

A portland cement plant is a top-tier air emission source: the kiln system emits NOx, SO2, CO, particulate matter, and hazardous air pollutants including mercury and HCl, and the surrounding quarry, crushers, mills, and material handling add dozens more emission points. There is no permit-by-rule shortcut at this scale — cement plants sit squarely in major source territory.

1Case-by-case NSR permit with PSD review

Every new kiln or major modification requires a case-by-case New Source Review permit under 30 TAC Chapter 116 — and because portland cement plants are one of the federally listed source categories, the PSD major source threshold drops to 100 tons per year instead of the default 250. In practice, every integrated plant is PSD-major, which means:

  • Best Available Control Technology (BACT) analysis for every pollutant — SNCR for NOx, baghouses for PM, scrubbers or inherent scrubbing for SO2
  • Air dispersion modeling against the NAAQS and PSD increments
  • Public notice and comment, with cement plants among the most frequent targets of contested case hearings in Texas — Midlothian and IH-35 corridor plants draw organized opposition
  • Pre-construction requirement: no construction until the permit issues

Realistic timeline for a greenfield plant: 18–36 months. Kiln modifications and expansions at existing sites typically run 12–24 months when PSD is triggered; smaller amendments move faster.

2Title V Federal Operating Permit

Every integrated cement plant in Texas holds a site-specific Title V permit — potential to emit far exceeds the 100 tpy major source threshold, and no general operating permit covers cement manufacturing. Title V consolidates every applicable requirement (NSR conditions, NESHAP, NSPS, Chapter 117) into one operating permit with semiannual deviation reporting and annual compliance certification. Renewals every five years are a significant compliance event, and permit revisions track each NSR amendment.

3Chapter 117 cement kiln NOx rules

Texas regulates cement kiln NOx directly under 30 TAC Chapter 117 ↗ as part of the ozone State Implementation Plan:

  • Ellis County: mandatory source cap NOx requirements for Midlothian-area kilns — a hard, county-specific emissions budget tied to the DFW ozone nonattainment area
  • Bexar, Comal, Ellis, Hays, and McLennan counties: kiln-specific NOx emission limits for units placed in service before December 31, 1999
  • CEMS requirements: continuous emissions monitoring with performance evaluations reported to TCEQ

With the San Antonio region's ozone nonattainment status tightening, Chapter 117 obligations for IH-35 corridor kilns are a moving target worth monitoring.

4Federal standards wired into the permits

Two federal programs define much of a cement plant's compliance workload, enforced through the NSR and Title V permits:

  • NESHAP Subpart LLL — the Portland Cement MACT: emission limits for mercury, HCl, total hydrocarbons, and PM, with continuous monitoring and stack testing obligations
  • NSPS Subpart F — new source performance standards for kilns, clinker coolers, and affected material handling systems

Plants burning alternative fuels (tires, non-hazardous secondary materials) face additional combustion rules and TCEQ authorization for the fuel switch — a common permit amendment in recent years.

5Quarry, crusher, and batch plant authorizations

Most Texas cement plants sit on their own limestone quarry. The quarry side brings its own stack of authorizations: rock crusher standard permits or NSR authorization for primary and secondary crushing, blasting-related dust controls, and — if the site hosts a ready-mix operation — a separate Concrete Batch Plant Standard Permit.

Don't confuse the two facility types: a cement plant manufactures cement in a kiln (major source, multi-year permitting); a concrete batch plant mixes cement into concrete (standard permit, weeks to months).

6Stormwater and water permits

  • Construction GP (TXR150000) ↗: required before earthwork disturbing 1+ acre — SWPPP, NOI, and site notices for what is invariably a large disturbed footprint
  • Multi-Sector General Permit (TXR050000): operating plants and quarries need industrial stormwater coverage with benchmark monitoring for sector-specific pollutants
  • Quarry dewatering and process water: discharges require TPDES authorization; many plants recycle process water to avoid individual permits
  • Edwards Aquifer (30 TAC Chapter 213): quarries and plants over the recharge or contributing zones — relevant along the IH-35 corridor — need TCEQ-approved Water Pollution Abatement Plans before construction
At a glance

Texas cement plant permit timeline.

Typical ranges, not guarantees. Contested case hearings are common for cement plant permits and can add 12+ months to NSR actions.

PermitAgencyWhen requiredTypical timeline
Case-by-case NSR + PSDTCEQNew kilns, major modifications; before construction18–36 months (greenfield); 12–24 (expansion)
NSR amendment (minor)TCEQSmaller changes, fuel switches3–9 months
Title V permit / revisionTCEQAll integrated plants; revisions per NSR changeInitial ~1–2 years; revisions vary
Chapter 117 NOx complianceTCEQKilns in covered countiesOngoing (CEMS, caps, reporting)
Rock crusher / quarry authorizationTCEQCo-located crushingStandard permit: ~1–4 months
Construction GP (TXR150000)TCEQ≥1 acre disturbance; before earthworkNOI: ~7 days after filing
MSGP (TXR050000)TCEQOperating plant + quarryNOI-based; ~30 days
Edwards Aquifer WPAPTCEQRecharge/contributing zone sites~3–6 months
FAQ

Texas cement plant permitting, answered.

What TCEQ permits does a cement plant need in Texas?+

A portland cement plant needs a case-by-case New Source Review air permit with PSD review (cement plants are on the federal 100-ton major source list), a Title V operating permit, Chapter 117 cement kiln NOx compliance in covered counties, construction and industrial stormwater coverage, and typically co-located quarry and crusher authorizations.

Is a cement plant the same as a concrete batch plant for permitting?+

No. A cement plant manufactures cement in a kiln and requires major NSR/PSD and Title V permitting — one of the heaviest air permit lifts in Texas. A concrete batch plant mixes cement with aggregate and water and typically qualifies for TCEQ's Concrete Batch Plant Standard Permit, a far simpler authorization.

How long does TCEQ permitting take for a cement plant?+

A greenfield cement plant is a multi-year effort: 18–36 months is realistic for the NSR/PSD permit including modeling, public notice, and a likely contested case hearing. Kiln modifications and capacity expansions at existing plants generally move faster but still run 12–24 months when PSD is triggered.

What are the main emission sources at a cement plant?+

The kiln system dominates — NOx, SO2, CO, particulate matter, and hazardous air pollutants including mercury and HCl. Other sources include the raw mill, clinker cooler, finish mills, material handling and transfer points, quarry blasting and crushing, and road dust.

Where are cement plants located in Texas?+

Texas is the nation's largest cement producer, with roughly ten integrated plants clustered where limestone geology meets demand: Ellis County (Midlothian) south of Dallas-Fort Worth, the New Braunfels-San Antonio corridor along IH-35, plus plants in West Texas and the Hill Country.

Track cement plant permits as they move.

Cement plant expansions surface in TCEQ's docket as permit amendments long before press releases — and contested case hearings can reshape projects for years. PermitPulse monitors TCEQ air permit filings daily and alerts you to new applications, amendments, and hearing requests for any Texas cement plant.

No credit card · 1 watch free forever

This article summarizes publicly available regulatory and market information for general informational purposes only — it is not legal, engineering, or professional advice. Sources: TCEQ — Controlling NOx Emissions from Cement Kilns · EPA — Texas SIP Cement Kiln Rules · TCEQ Construction Stormwater GP · Amrize Midlothian Expansion · Amrize $900M Investment Program · CRH Hunter Plant Acquisition · TxDOT Hydraulic Cement Producer List. Figures and timelines may change; always confirm against current rules and filings before acting.